[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894209":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894209,580,1,"单选题","为合理划分发承包双方的合同风险，对于招标工程，在施工合同中约定的基准日期一般为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标文件中规定的提交投标文件截止时间前的第28天",true,{"key":16,"text":17,"correct":18},"B","招标文件中规定的提交投标文件截止时间前的第42天",false,{"key":20,"text":21,"correct":18},"C","施工合同签订前的第28天",{"key":23,"text":24,"correct":18},"D","施工合同签订前的第42天","对于实行招标的建设工程，一般以施工招标文件中规定的提交投标文件的截止时间前的第 28天作为基准日。因此，正确选项为 A。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]