[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894197":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894197,580,1,"单选题","根据《2017届预算定额》，某预制钢筋混凝土方桩的单位工程工程量为150m3，则相应的人工、机械乘以系数（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1.50",false,{"key":16,"text":17,"correct":14},"B","1.43",{"key":19,"text":20,"correct":21},"C","1.25",true,{"key":23,"text":24,"correct":14},"D","1.15","本题考查的是《2017届房屋建筑与装饰工程预算定额》基本内容。当单位工程的桩基工程量少于某对应数量时，相应项目人工、机械乘以系数1.25。预制钢筋混凝土方桩200m3；预应力钢筋混凝土管桩1000m；预制钢筋混凝土板桩100m3；钻孔、旋挖成孔灌注桩150m3；沉管、冲孔成孔灌注桩100m3，钢管桩50t。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]