[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894194":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894194,580,1,"单选题","根据《2017届预算定额》，某工程采用人工挖沟槽土方，沟槽深度为7m，相应项目人工系数为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.43",false,{"key":16,"text":17,"correct":18},"B","1.25",true,{"key":20,"text":21,"correct":14},"C","1.18",{"key":23,"text":24,"correct":14},"D","1.15","本题考查的是《2017届房屋建筑与装饰工程预算定额》基本内容。人工挖一般土方、沟槽、基坑深度超过6m时，6m\u003C深度≤7m，按深度≤6m相应项目人工乘以系数1.25；7m\u003C深度≤8m；按深度≤6m相应项目人工乘以系数1.25；以此类推。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]