[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894193,580,1,"单选题","实物量法编制施工图换算时，计算并复核工程量后紧接着进行的工作是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","套用定额单价，计算人材机费用",false,{"key":16,"text":17,"correct":18},"B","套用定额，计算人材机消耗量",true,{"key":20,"text":21,"correct":14},"C","汇总人材机费用",{"key":23,"text":24,"correct":14},"D","计算管理费等其他各项费用","实物量法编制施工图预算的步骤：（1）准备资料、熟悉施工图纸。（2）列项并计算工程量。（3）套用消耗量定额，计算人工、材料、机具台班消耗量。（4）计算并汇总人工费、材料费和施工机具使用费。（5）计算其他各项费用，汇总造价。（6）复核、填写封面、编制说明。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]