[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894187":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894187,580,1,"单选题","下列关于工程量清单项目编码的表述中，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目编码以五级设置，一至四级按计价规范附录的规定设置",false,{"key":16,"text":17,"correct":18},"B","特征相同的单位工程可采用相同的项目编码",true,{"key":20,"text":21,"correct":14},"C","项目编码中第二级表示附录分类顺序码",{"key":23,"text":24,"correct":14},"D","项目编码中第五级由招标人针对招标工程项目具体编制","本题考查的是分部分项工程项目清单。选项B错误，当同一标段（或合同段）的一份工程量清单中含有多个单位工程且工程量清单是以单位工程为编制对象时，在编制工程量清单时应特别注意对项目编码10至12位的设置不得有重码的规定。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]