[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894186":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},894186,580,1,"单选题","根据《房屋建筑与装饰工程量计算规范》，措施项目清单的编制依据不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工现场情况",false,{"key":16,"text":17,"correct":14},"B","常规施工方案",{"key":19,"text":20,"correct":14},"C","拟定的招标文件",{"key":22,"text":23,"correct":24},"D","施工组织设计",true,"本题考查的是措施项目清单。措施项目清单的编制依据主要有：（1）施工现场情况、地勘水文资料、工程特点；（2）常规施工方案；（3）与建设工程有关的标准、规范、技术资料；（4）拟定的招标文件；（5）建设工程设计文件及相关资料。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]