[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894168":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},894168,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），下列关于预制钢筋混凝土方桩、预制钢筋混凝土管桩的计量，说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预制钢筋混凝土方桩、预制钢筋混凝土管桩以米计量",false,{"key":16,"text":17,"correct":14},"B","按设计图示尺寸以桩长（包括桩尖）计算",{"key":19,"text":20,"correct":14},"C","按设计图示截面积乘以桩长（包括桩尖）以实体积计算",{"key":22,"text":23,"correct":24},"D","按设计图示截面积乘以桩长（不包括桩尖）以实体积计算",true,"本题考查的是桩基础工程。预制钢筋混凝土方桩、预制钢筋混凝土管桩以米计量，按设计图示尺寸以桩长（包括桩尖）计算；或以“立方米”计量。按设计图示截面积乘以桩长（包括桩尖）以实体积计算；或以“根”计量，按设计图示数量计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]