[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894163":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894163,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），关于土石方回填工程量计算，说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","回填土方项目特征应包括填方来源及运距",true,{"key":16,"text":17,"correct":18},"B","室内回填应扣除间隔墙所占体积",false,{"key":20,"text":21,"correct":18},"C","场地回填按设计回填尺寸以面积计算",{"key":23,"text":24,"correct":18},"D","基础回填不扣除基础垫层所占面积","本题考查的是土石方工程工程量。选项B，室内回填：主墙间净面积乘以回填厚度，不扣除间隔墙；选项C，场地回填按回填面积乘以平均回填厚度；选项D，基础回填按挖方清单项目工程量减去自然地坪以下埋设的基础体积包括基础垫层及其他构筑物。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]