[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894157":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894157,580,1,"单选题","措施项目清单编制中，下列适用于以“项”为单位计价的措施项目费是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已完工程及设备保护费",true,{"key":16,"text":17,"correct":18},"B","超高施工增加费",false,{"key":20,"text":21,"correct":18},"C","大型机械设备进出场及安拆费",{"key":23,"text":24,"correct":18},"D","施工排水、降水费","本题考查的是土建工程工程量清单的编制方法。措施项目清单按项计算的有：安全文明施工费、夜间施工增加、非夜间施工照明费二次搬运费、冬雨季施工增加费、地上、地下设施、建筑物的临时保护设施费、已完工程及设备保护费；采用综合单价计价的有：脚手架费、混凝土模板及支架（撑）费、垂直运输费超高施工增加费、大型机械设备进出场及安拆费、施工排水、降水费。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]