[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894149":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894149,580,1,"单选题","根据《房屋建筑与装修工程工程量清单计算规范》，混凝土及钢筋混凝土工程量计算，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","现浇有梁板主梁、次梁按体积并入楼板工程量中计算",true,{"key":16,"text":17,"correct":18},"B","无梁板柱帽按体积并入零星项目工程量中计算",false,{"key":20,"text":21,"correct":18},"C","弧形楼梯不扣除宽度小于600mm的楼梯井",{"key":23,"text":24,"correct":18},"D","整体楼梯按水平投影面积计算，不包括与楼板连接的梯梁所占面积","有梁板（包括主、次梁与板）按梁、板体积之和计算。无梁板按板和柱帽体积之和计算，各类板伸入墙内的板头并入板体积内计算。楼梯，按设计图示尺寸以水平投影面积计算，不扣除宽度小于或等于 500mm的楼梯井所占面积。整体楼梯（包括直形楼梯、弧形楼梯）水平投影面积包括休息平台、平台梁、斜梁和楼梯的连接梁。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]