[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894144":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894144,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），现浇混凝土墙工程量应（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","扣除突出墙面部分体积",false,{"key":16,"text":17,"correct":14},"B","不扣除面积为0.33m2孔洞体积",{"key":19,"text":20,"correct":21},"C","将伸入墙内的梁头计入",true,{"key":23,"text":24,"correct":14},"D","扣除预埋铁件体积","现浇混凝土墙包括直形墙、弧形墙、短肢剪力墙、挡土墙。按设计图示尺寸以体积计算。不扣除构件内钢筋，预埋铁件所占体积，扣除门窗洞口及单个面积大于 0.3m2的孔洞所占体积，墙垛及突出墙面部分并入墙体体积内计算。当梁与混凝土墙连接时，梁的长度应计算到混凝土墙的侧面。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]