[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894142":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894142,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013）规定，关于土方的项目列项或工程量计算正确的为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建筑物场地厚度为350mm的挖土应按平整场地项目列项",false,{"key":16,"text":17,"correct":14},"B","挖一般土方的工程量通常按开挖虚方体积计算",{"key":19,"text":20,"correct":21},"C","基础土方开挖需区分沟槽、基坑和一般土方项目分别列项",true,{"key":23,"text":24,"correct":14},"D","冻土开挖工程量需按夯实后体积计算","厚度＞±300mm的竖向布置挖土或山坡切土应按一般土方项目编码列项，故 A错误。挖一般土方按设计图示尺寸以体积计算，土石方体积应按挖掘前的天然密实体积计算，故 B错误。冻土按设计图示尺寸开挖面积乘以厚度以体积计算，故 D错误。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]