[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894125":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894125,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500－2013），关于金属结构工程量计算，说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钢管柱牛腿工程量列入其他项目中",false,{"key":16,"text":17,"correct":18},"B","钢网架按设计图示尺寸以质量计算",true,{"key":20,"text":21,"correct":14},"C","金属结构工程量应扣除孔眼、切边质量",{"key":23,"text":24,"correct":14},"D","金属结构工程量应增加铆钉、螺栓质量","本题考查的是金属工程。钢网架按设计图示尺寸以质量计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]