[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894123":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894123,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500－2013），关于金属结构工程工程量计算的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不扣除孔眼、切边、切肢的质量，焊条、铆钉、螺栓等质量不另增加",false,{"key":16,"text":17,"correct":18},"B","钢管柱上牛腿的质量不增加",true,{"key":20,"text":21,"correct":14},"C","压型钢板墙板，按设计图示尺寸以铺挂面积计算",{"key":23,"text":24,"correct":14},"D","金属网栏按设计图示尺寸以面积计算","本题考查的是金属工程。钢管柱上的节点板、加强坏、内衬管、牛腿等并入钢管柱工程量内。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]