[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894121":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894121,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500－2013），关于预制混凝土构件工程量计算，说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预制组合屋架，按设计图示尺寸以体积计算，不扣除预埋铁件所占体积",true,{"key":16,"text":17,"correct":18},"B","预制网架板，按设计图示尺寸以体积计算，不扣除孔洞占体积",false,{"key":20,"text":21,"correct":18},"C","预制空心板，按设计图示尺寸以体积计算，不扣除空心板空洞所占体积",{"key":23,"text":24,"correct":18},"D","预制混凝土楼梯按设计图示尺寸以体积计算，不扣除空心踏步板空洞体积","本题考查的是混凝土及钢筋混凝土工程。空心板、网架板工程量以立方米计量时，按设计图示尺寸以体积计算。不扣除单个面积＜300mm×300mm的孔洞所占体积，扣除空心板空洞体积；以块计量时，按设计图示数量计算。以块计量时，项目特征必须描述单件体积。预制混凝土楼梯工程量以立方米计量的，按设计图示尺寸以体积计算，扣除空心踏步板空洞体积；以段计量的，按设计图示数量计算。以段计量时，项目特征必须描述单件体积。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]