[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894111":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894111,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500－2013），下列工程量计算的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","砂石土桩只能按根数计算",false,{"key":16,"text":17,"correct":18},"B","粉喷桩按设计图示尺寸以桩长（包括桩尖）计算",true,{"key":20,"text":21,"correct":14},"C","地下连续墙按长度计算",{"key":23,"text":24,"correct":14},"D","锚杆支护按支护土体体积计算","本题考查的是地基处理与边坡支护工程。砂石桩工程量，可按设计图示尺寸的桩长（包括桩尖）以米计算，或按设计桩截面乘以桩长（包括桩尖） 以体积计算；地下连续墙工程量按设计图示墙中心线长乘以厚度乘以槽深以体积计算；锚杆（锚索） 和土钉的工程量以米计量时，按设计图示尺寸以钻孔深度计算；以根计量时，按设计图示数量计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]