[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894105":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894105,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500－2013），土石方工程中，建筑物场地厚度在±30cm以内的，平整场地工程量应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按建筑物自然层面积计算",false,{"key":16,"text":17,"correct":18},"B","按建筑物首层建筑面积计算",true,{"key":20,"text":21,"correct":14},"C","按建筑有效面积计算",{"key":23,"text":24,"correct":14},"D","按设计图示厚度计算","本题考查的是土石方工程。平整整场地工程量按设计图示尺寸以建筑物首层建筑面积以m2计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]