[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894091":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894091,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013）规定，关于基坑支护工程量计算正确的为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","地下连续墙按设计图示墙中心线长度计算",false,{"key":16,"text":17,"correct":18},"B","预制钢筋混凝土板桩按设计图示数量以根计算",true,{"key":20,"text":21,"correct":14},"C","钢板桩按设计图示数量以根计算",{"key":23,"text":24,"correct":14},"D","喷射混凝土按设计图示面积乘以喷层厚度以体积计算","地下连续墙按设计图示墙中心线长乘以厚度乘以槽深以体积计算。钢板桩按设计图示尺寸以质量计算，以平方米计量，按设计图示墙中心线长乘以桩长以面积计算。喷射混凝土（水泥砂浆）按设计图示尺寸以面积计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]