[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894003":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894003,580,1,"单选题","单位工程施工组织设计中施工顺序的确定应包含于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工条件分析",false,{"key":16,"text":17,"correct":18},"B","施工进度计划",true,{"key":20,"text":21,"correct":14},"C","资源需求计划",{"key":23,"text":24,"correct":14},"D","施工平面设计","本题考查的是单位工程施工组织设计。施工进度计划是以施工方案为基础，根据规定工期和各类资源的供应条件，遵循各施工过程合理的工艺顺序，统筹安排各项施工活动，为各施工过程指明一个确定的施工日期，并以此为依据确定施工作业所必需的各种资源供应计划。施工进度计划通常采用横道图或网络图表达。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]