[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894002":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894002,580,1,"单选题","在施工组织总设计中，能够确定关键工作、关键线路和进行工期优化的总进度计划表达方式为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图",false,{"key":16,"text":17,"correct":18},"B","网络图",true,{"key":20,"text":21,"correct":14},"C","S曲线",{"key":23,"text":24,"correct":14},"D","香蕉曲线","本题考查的是施工组织总设计。当采用网络图表达施工总进度计划时，应确定关键工作、关键线路和进行工期优化。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]