[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893976,580,1,"单选题","地下连续梁在进行槽段内混凝土浇筑时，钢筋笼就位后应及时浇筑混凝土，导管埋入混凝面的深度适宜的是（ ）m。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.5",false,{"key":16,"text":17,"correct":18},"B","3.0",true,{"key":20,"text":21,"correct":14},"C","4.5",{"key":23,"text":24,"correct":14},"D","6.0","本题考查的是地下连续墙施工技术。混凝土浇筑过程中，导管埋入混凝土面下的深度保持在2.0m-4.0m之间，直至混凝土浇灌到地下连续墙墙顶附近，方可将导管的埋入深度减为lm左右，并将导管适当地做上下运动，促使混凝土流出导管。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]