[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893964,580,1,"单选题","关于编制施工总进度计划的说法，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工总进度计划越细越好",true,{"key":16,"text":17,"correct":18},"B","施工总进度计划一般用图表表示，通常有横道图和网络图两种",false,{"key":20,"text":21,"correct":18},"C","当采用横道图表达总进度计划时，横道图上应表达出各施工项目的开工、竣工时间及其施工持续时间",{"key":23,"text":24,"correct":18},"D","当采用网络图表达施工总进度计划时，应确定关键工作、关键线路和进行工期优化","本题考查的是施工总进度计划。施工总进度计划属于控制性计划，不宜过细。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]