[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893949":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893949,580,1,"单选题","钢筋混凝土预制桩的运输和堆放应满足以下要求（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","混凝土强度达到设计强度的70%方可运输",false,{"key":16,"text":17,"correct":18},"B","混凝土强度达到设计强度的100%方可运输",true,{"key":20,"text":21,"correct":14},"C","堆放层数不宜超过10层",{"key":23,"text":24,"correct":14},"D","不同规格的桩按上小下大的原则堆放","钢筋混凝土预制桩应在混凝土达到设计强度的 70%方可起吊；达到 100%方可运输和打桩。堆放层数不宜超过 4层。不同规格的桩应分别堆放。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]