[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893940":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893940,580,1,"单选题","预应力混凝土构件先张法施工工艺流程正确的为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安骨架、钢筋－张拉－安底、侧模－浇灌－养护－拆模－放张",false,{"key":16,"text":17,"correct":18},"B","安底模、骨架、钢筋－张拉－支侧模－浇灌－养护－拆模－放张",true,{"key":20,"text":21,"correct":14},"C","安骨架－安钢筋－安底、侧模－浇灌－张拉－养护－放张－拆模",{"key":23,"text":24,"correct":14},"D","安底模、侧模－安钢筋－张拉－浇灌－养护－放张－拆模","本题考查的是建筑工程主体结构施工技术。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]