[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893927":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893927,580,1,"单选题","关于钢筋混凝土预制桩加工制作，说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","长度在10m以上的桩必须工厂预制",false,{"key":16,"text":17,"correct":14},"B","现场预制桩不采用重叠法制作",{"key":19,"text":20,"correct":14},"C","桩的强度达到设计强度的70%方可运输",{"key":22,"text":23,"correct":24},"D","桩的强度达到设计强度的70%方可起吊",true,"本题考查的是地基与基础工程施工技术。长度小于10m的短桩，一般多在工厂预制；较长的桩，因不便运输，通常在打桩现场附近；预制钢筋混凝土预制桩应在混凝土达到设计强度的70%时方可起吊，达到100%时方可运输和打桩。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]