[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893926":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893926,580,1,"单选题","钢筋混凝土预制桩起吊时，混凝土强度应至少达到设计强度的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30%",false,{"key":16,"text":17,"correct":14},"B","50%",{"key":19,"text":20,"correct":21},"C","70%",true,{"key":23,"text":24,"correct":14},"D","100%","本题考查的是地基与基础工程施工技术。钢筋混凝土预制桩应在混凝土达到设计强度的70%时方可起吊，达到100%时方可运输和打桩。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]