[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893922":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893922,580,1,"单选题","采用明排水法开挖基坑，在基坑开挖过程中设置的集水坑应（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","布置在基础范围以内",false,{"key":16,"text":17,"correct":14},"B","布置在基坑底部中央",{"key":19,"text":20,"correct":21},"C","布置在地下水走向的上游",true,{"key":23,"text":24,"correct":14},"D","经常低于挖土面1.0m以上","本题考查的是土石方工程施工技术。明排水是在基坑开挖过程中，逐层在坑底设置集水坑，由坑底周围或中央开挖的排水沟将地下渗水导入集水坑，然后用水泵抽走。集水坑应设置在基础范围以外、地下水走向的上游",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]