[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893911":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893911,580,1,"单选题","先张法预应力混凝土构件施工，其工艺流程为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","支底模-支侧模-张拉钢筋-浇筑混凝土-养护、拆模-放张钢筋",false,{"key":16,"text":17,"correct":14},"B","支底模-张拉钢筋-支侧模-浇筑混凝土-放张钢筋-养护、拆模",{"key":19,"text":20,"correct":21},"C","支底模-预应力钢筋安放-张拉钢筋-支侧模-浇混凝土-拆模-放张钢筋",true,{"key":23,"text":24,"correct":14},"D","支底模-钢筋安放-支侧模-张拉钢筋-浇筑混凝土-放张钢筋-拆模","先张拉预应力钢筋再支侧模，故 A错。拆模后放松预应力钢筋，故 B、D错。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]