[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893908":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893908,580,1,"单选题","对混凝土采用自然养护时，应在浇筑完毕后的（）以内对混凝土加以覆盖并保湿养护。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6小时",false,{"key":16,"text":17,"correct":18},"B","12小时",true,{"key":20,"text":21,"correct":14},"C","18小时",{"key":23,"text":24,"correct":14},"D","24小时","应在浇筑完毕后的 12h以内对混凝土加以覆盖并保湿养护；干硬性混凝土应于浇筑完毕后立即进行养护。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]