[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893902":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893902,580,1,"单选题","设置钢筋混凝土构造柱的砖墙砌体，施工时应（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先砌墙后浇构造柱",true,{"key":16,"text":17,"correct":18},"B","从每层柱脚开始马牙槎先进后退",false,{"key":20,"text":21,"correct":18},"C","先浇构造柱后砌墙",{"key":23,"text":24,"correct":18},"D","构造柱浇筑和砌墙砌筑同时进行","按先砌墙后浇灌混凝土柱的施工顺序制成。墙体应砌成马牙槎。马牙槎凹凸尺寸不宜小于60mm，高度不应超过 300mm，马牙槎应先退后进，对称砌筑。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]