[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893900,580,1,"单选题","静力压桩正确的施工工艺流程是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定位—吊桩—对中—压桩—接桩—压桩—送桩—切割桩头",true,{"key":16,"text":17,"correct":18},"B","吊桩—定位—对中—压桩—送桩—压桩—接桩—切割桩头",false,{"key":20,"text":21,"correct":18},"C","对中—吊桩—插桩—送桩—静压—接桩—压桩—切割桩头",{"key":23,"text":24,"correct":18},"D","吊桩—定位—压桩—送桩—接桩—压桩—切割桩头","静力压桩由于受设备行程的限制，在一般情况下是分段预制、分段压入、逐段压入、逐段接长，其施工工艺顺序为：测量定位→压桩机就位→吊桩、插桩→桩身对中调制→静压沉桩→接桩（下段桩上端距地面 0.5～1m时接上段桩）→逐段重复静压沉桩和接桩→送桩→终止压桩→切割桩头。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]