[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893833":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893833,580,1,"单选题","对于不能计算工程量的措施项目，当按施工方案计算措施费时，若无“计算基础”和“费率”数值，则（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以定额计价为计算基础，以国家、行业、地区定额中相应的费率计算金额",false,{"key":16,"text":17,"correct":14},"B","以“定额人工费+定额机械费”为计算基础，以国家、行业、地区定额中相应费率计算金额",{"key":19,"text":20,"correct":21},"C","只填写“金额”数值，在备注中说明施工方案出处或计算方法",true,{"key":23,"text":24,"correct":14},"D","备注中说明中计算方法，补充填写“计算基础”和“费率”","本题考查的是措施项目清单。按施工方案计算的措施费，若无“计算基础”和“费率”的数值，也可只填“金额”数值，但应在备注栏说明施工方案出处或计算方法。因此，正确选项为 C。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]