[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893825":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893825,580,1,"单选题","完成某预算定额项目单位工程量的基本用工为2.8工日，辅助用工为0.7工日，超运距用工为0.9工日，人工幅度差系数为10%，该定额的人工工日消耗量为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4.84",true,{"key":16,"text":17,"correct":18},"B","4.75",false,{"key":20,"text":21,"correct":18},"C","4.56",{"key":23,"text":24,"correct":18},"D","4.68","人工消耗量＝基本用工＋超运距用工＋辅助用工＋人工幅度差用工；人工幅度差用工数量＝∑（基本用工＋超运距用工＋辅助用工）×人工幅度差系数。人工消耗量＝（2.8＋0.7＋0.9）工日＋（2.8＋0.7＋0.9）工日×10%＝4.84工日。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]