[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893820":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893820,580,1,"单选题","完成某分部分项工程 1m3需基本用工 0.5 工日，超运距用工 0.05 工日，辅助用工 0.1 工日。如人工幅度差系数为 10%，则该工程预算定额人工工日消耗量为（ ）工日\u002F10m3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","6.05",false,{"key":16,"text":17,"correct":14},"B","5.85",{"key":19,"text":20,"correct":14},"C","7.00",{"key":22,"text":23,"correct":24},"D","7.15",true,"本题考查的是预算定额及其基价编制。人工幅度差=（基本用工+辅助用工+超运距用工）×人工幅度差系数=（0.5+0.05+0.1）×10%=0.065（工日\u002F10m3），人工工日消耗量=基本用工+辅助用工+超运距用工+人工幅度差=0.5+0.05+0.1+0.065=0.715（工日\u002Fm3），即 7.15 工日 \u002F10m3。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]