[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893819":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893819,580,1,"单选题","下列用时中，同时包含在劳动定额和预算定额人工消耗量中的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","隐蔽工程验收的影响时间",false,{"key":16,"text":17,"correct":14},"B","工序搭接发生的停歇时间",{"key":19,"text":20,"correct":21},"C","不可避免的中断时间",true,{"key":23,"text":24,"correct":14},"D","加工材料所需的时间","本题考查的是预算定额及其基价编制。超运距用工、辅助用工、人工幅度差在劳动定额中不包括，预算定额中应该考虑的。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]