[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893814":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893814,580,1,"单选题","实物量法编制施工图换算时，计算并符合工程量后紧接着进行的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","套用定额单价，计算人材机费用",true,{"key":16,"text":17,"correct":18},"B","套用定额，计算人材机消耗量",false,{"key":20,"text":21,"correct":18},"C","汇总人材机费用",{"key":23,"text":24,"correct":18},"D","计算管理费等其他各项费用","用实物量法编制单位工程施工图预算，就是根据施工图计算的各分项工程量分别乘以地区定额中人工、材料、施工机具台班的定额消耗量，分类汇总得出该单位工程所需的全部人工、材料、施工机具台班消耗数量，然后再乘以当时当地人工工日单价、各种材料单价、施工机械台班单价、施工仪器仪表台班单价，求出相应的人工费、材料费、机具使用费。企业管理费、利润、规费和税金等费用计取方法与工料单价法相同。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]