[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893812":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893812,580,1,"单选题","下列用工项目中，属于预算定额与劳动定额人工幅度差的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","机械土方工程配合用工",false,{"key":16,"text":17,"correct":14},"B","超过预算定额取定运距增加的运输用工C",{"key":19,"text":20,"correct":21},"C","班组操作地点转移用工",true,{"key":23,"text":24,"correct":14},"D","机械维修引起的停歇时间","本题考查的是预算定额及其基价编制。人工幅度差内容包括：（1）各工种间的工序搭接及交叉作业相互配合或影响所发生的停歇用工；（2）施工过程中，移动临时水电线路而造成的影响工人操作的时间；（3）质量检查和隐蔽工程验收工作的影响；（4）班组操作地点转移用工；（5）工序交接时对前一工序不可避免的修整用工；（6）施工中不可避免的其他零星用工。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]