[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893798":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893798,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），投标人认为最高投标限价编制不符合规范规定的，应在最高投标限价公布后（ ）d内提交书面申请。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","5",true,{"key":20,"text":21,"correct":14},"C","7",{"key":23,"text":24,"correct":14},"D","10","投标人经复核认为招标人公布的最高投标限价未按照《建设工程工程量清单计价规范》（GB 50500—2013）的规定进行编制的，应在最高投标限价公布后5d内向招投标监督机构和工程造价管理机构投诉。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]