[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893795,580,1,"单选题","关于投标报价，下列说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总价措施项目均由投标人自主报价",false,{"key":16,"text":17,"correct":14},"B","暂列金额依据招标工程量清单总说明，结合项目管理规划自主填报",{"key":19,"text":20,"correct":14},"C","暂估价依据询价情况填报",{"key":22,"text":23,"correct":24},"D","投标人对投标报价的任何优惠均应反映在相应清单项目的综合单价中",true,"总价措施项目费由投标人自主确定，但其中安全文明施工费必须按照国家或省级、行业建设主管部门的规定计价，不得作为竞争性费用，故 A 选项错误。暂列金额应按照招标人提供的其他项目清单中列出的金额填写，不得变动，故 B 选项错误。材料、工程设备暂估单价和专业工程暂估价均由招标人提供，投标人不得变动和更改，故 C 选项错误。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]