[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893790":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893790,580,1,"单选题","实行工程量清单计价的招标工程，投标人可完全自主报价的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":18},"B","总承包服务费",true,{"key":20,"text":21,"correct":14},"C","专业工程暂估价",{"key":23,"text":24,"correct":14},"D","措施项目费","A项，暂列金额应按照招标工程量清单中列出的金额填写，不得变动。B项，总承包服务费应根据招标工程量列出的专业工程暂估价内容和供应材料、设备情况，按照招标人提出协调、配合与服务要求和施工现场管理需要自主确定。C项，暂估价不得变动和更改。暂估价中的材料、工程设备必须按照暂估单价计入综合单价；专业工程暂估价必须按照招标工程量清单中列出的金额填写。D项，措施项目中的安全文明施工费应按照国家或省级、行业主管部门的规定计算确定。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]