[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893787":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893787,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），关于提前竣工的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","招标人压缩的工期天数不得超过定额工期的50%",false,{"key":16,"text":17,"correct":14},"B","工程实施过程中，发包人要求合同工程提前竣工，可以不征求承包人意见",{"key":19,"text":20,"correct":21},"C","发承包双方约定提前竣工每日历天应补偿额度，与结算款一并支付",true,{"key":23,"text":24,"correct":14},"D","赶工费用包括人工费、材料费、机械费以及履约保函手续费的增加","A项，招标人应依据相关工程的工期定额合理计算工期，压缩的工期天数不得超过定额工期的20%，超过者，应在招标文件中明示增加赶工费用。B项，工程实施过程中，发包人要求合同工程提前竣工，应征得承包人同意。D项，赶工费用主要包括：人工费的增加；材料费的增加；机械费的增加。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]