[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893786,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），关于合同工期的说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人要求合同工程提前竣工的，应承担承包人由此增加的提前竣工费用",true,{"key":16,"text":17,"correct":18},"B","招标人压缩的工期天数不得超过定额工期的30%",false,{"key":20,"text":21,"correct":18},"C","招标人压缩的工期天数超过定额工期的20%但不超过30%时，不额外支付赶工费用",{"key":23,"text":24,"correct":18},"D","工程实施过程中，发包入要求合同工程提前竣工的，承包入必须采取加快工程进度的措施","AD两项，工程实施过程中，发包人要求合同工程提前竣工的，应征得承包人同意后与承包人商定采取加快工程进度的措施，并应修订合同工程进度计划。发包人应承担承包人由此增加的提前竣工（赶工补偿）费用。BC两项，工程发包时，招标人应当依据相关工程的工期定额合理计算工期，压缩的工期天数不得超过定额工期的20%，将其量化。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]