[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893785":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893785,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），采用清单计价的某分部分项工程，最高投标限价的综合单价为350元，承包人投标报价的综合单价为300元，该工程投标报价总的下浮率为5%，结算时，该分部分项工程工程量比清单工程量增加了16%，且合同未确定综合单价调整方法，则对该综合单价的正确处理方式是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整为257元",false,{"key":16,"text":17,"correct":14},"B","调整为282.63元",{"key":19,"text":20,"correct":21},"C","不做任何调整",true,{"key":23,"text":24,"correct":14},"D","调整为345元","偏差计算：300元\u002F350元＝85.71%，偏差为14.29%；根据公式：P0＞P2×（1－L）×（1－15%），可知，300元＞350元×（1－5%）×（1－15%）＝282.63元；则该项目的综合单价不予调整。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]