[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893784":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893784,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），签约合同中的暂估材料在确定单价以后，其相应项目综合单价的处理方式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在综合单价中用确定单价代替原暂估价，并调整企业管理费，不调整利润",false,{"key":16,"text":17,"correct":14},"B","在综合单价中用确定单价代替原暂估价，并调整企业管理费和利润",{"key":19,"text":20,"correct":14},"C","综合单价不做调整",{"key":22,"text":23,"correct":24},"D","在综合单价中用确定单价代替原暂估价，不再调整企业管理费和利润",true,"暂估材料或工程设备的单价确定后，在综合单价中只应取代原暂估单价，不应再在综合单价中涉及企业管理费或利润等其他费的变动。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]