[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893781":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893781,580,1,"单选题","关于工程量清单计价方式下竣工结算的编制原则，下列说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","措施项目费按双方确认的工程量乘以已标价工程量清单的综合单价计算",false,{"key":16,"text":17,"correct":14},"B","总承包服务费按已标价工程量清单的金额计算，不应调整",{"key":19,"text":20,"correct":14},"C","暂列金额应减去工程价款调整的金额，余额归承包人",{"key":22,"text":23,"correct":24},"D","工程实施过程中发承包双方已经确认的工程计量结果和合同价款，应直接进入结算",true,"A项，分部分项工程和措施项目中的单价项目应依据双方确认的工程量与已标价工程量清单的综合单价计算。B项，总承包服务费应依据合同约定金额计算，如发生调整的，以发承包双方确认调整的金额计算。C项，暂列金额应减去工程价款调整（包括索赔、现场签证）金额计算，如有余额归发包人。D项，发承包双方在合同工程实施过程中已经确认的工程计量结果和合同价款，在竣工结算办理中应直接进入结算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]