[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893779":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893779,580,1,"单选题","工程量清单中的暂估价是指（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程合同签订时尚未确定或不可预见的材料、工程设备采购费用",false,{"key":16,"text":17,"correct":14},"B","可能发生但暂时不能确定价格的材料、工程设备单价及分包工程费用",{"key":19,"text":20,"correct":21},"C","必然发生但暂时不能确定价格的材料、工程设备单价及专业工程费用",true,{"key":23,"text":24,"correct":14},"D","工程施工中可能发生的工程变更，合同调整及索赔等引起的工程费用","暂估价是指招标人在工程量清单中提供的用于支付必然发生但暂时不能确定价格的材料、设备（指计入建筑安装工程费的设备）的单价以及拟另行分包专业工程的金额。暂估价包括材料暂估单价、工程设备暂估单价和专业工程暂估价。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]