[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893778":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893778,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），当合同中没有约定时，对于任一招标工程量清单项目，如果因工程变更等原因导致工程量偏差超过（ ）时，合同单价应进行调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":18},"B","15%",true,{"key":20,"text":21,"correct":14},"C","10%",{"key":23,"text":24,"correct":14},"D","5%","对于任一招标工程量清单项目，如果因工程量偏差和工程变更等原因导致工程量偏差超过15%时，可进行调整。当工程量增加15%以上时，增加部分的工程量的综合单价应予调低；当工程量减少15%以上时，减少后剩余部分的工程量的综合单价应予调高。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]