[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893774":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893774,580,1,"单选题","某施工合同约定采用价格指数及价格调整公式调整价格差额，调价因素及有关数据见下表。某月完成进度款为 1500万元，则该月应当支付给承包人的价格调整金额为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-30.3",false,{"key":16,"text":17,"correct":18},"B","36.45",true,{"key":20,"text":21,"correct":14},"C","112.5",{"key":23,"text":24,"correct":14},"D","130.5","价格调整金额=1500×［0.3+（0.1×90\u002F80+0.1×102\u002F100+0.15×120\u002F110+0.15×110\u002F120+0.2×120\u002F115）-1］=36.45（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]