[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893772,580,1,"单选题","工程延误期间，因国家法律、行政法发生变化引起工程造价变化的，则（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人导致的工程延误，合同价款均应予调整",false,{"key":16,"text":17,"correct":14},"B","发包人导致的工程延误，合同价款均应予调整",{"key":19,"text":20,"correct":21},"C","不可抗力导致的工程延误，合同价款均应予调整",true,{"key":23,"text":24,"correct":14},"D","无论何种情况，合同价款均应予调整","若由于不可抗力导致了工程延误，则在延误期间内法律、行政法规变化的风险依然由发包人承担，即合同价款应予调整。如果由于承包人的原因导致的工期延误，按不利于承包人的原则调整合同价款。在工程延误期间国家的法律、行政法规和相关政策发生变化引起工程造价变化的，造成合同价款增加的，合同价款不予调整；造成合同价款减少的，合同价款予以调整。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]