[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893770":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893770,580,1,"单选题","关于计日工费用的确认和支付，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人应按照确认的计日工现场签证报告提出计日工项目的数量",true,{"key":16,"text":17,"correct":18},"B","发包人应根据已标价工程量清单中的工程数量和计日工单价确定",false,{"key":20,"text":21,"correct":18},"C","已标价工程量清单中没有计日工单价的，由发包人确定价格",{"key":23,"text":24,"correct":18},"D","已标价工程量清单中没有计日工单价的，由承包人确定价格","承包人应按照确认的计日工现场签证报告核实该类项目的工程数量，并根据核实的工程数量和承包人已标价工程量清单中的计日工单价计算，提出应付价款，B 错误；已标价工程量清单中没有该类计日工单价的，由发承包双方按工程变更的有关的规定商定计日工单价计算，CD 错误。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]